How did you handle a situation where you couldn't meet a deadline?
Palantir Technologies
Dropbox
Microsoft
Flexport
TikTok
Spotify
Palantir Technologies
Dropbox
Microsoft
Flexport
TikTok
Spotify
Realistic mock interview with instant feedback. Fully customized.
More interviews, more skills, more success.
3 answers from the community
Anonymous
S - Sales got a new client and they promised to create a product for them in 12 weeks.
T - As the program director, I was tasked to manage this end to end, when I reviewd the High level requirements, it was clear that we will not be able to deliver this entire application in just 12 weeks.
A - I immediately called a meeting with my team to brainstorm solutions and create a plan, and a roadmap to develop a MVP, that will have the essential features & enough UI for the client to start their work. But since we were working on 2 high visibility products already, I could sense some resistance from the team. I assured the team, that I will work with the client and will only get the most essential and minimal features out first, and can deliver much more when they actually have time. so we developed a plan to deliver one small feature every 2 weeks, so by the end of 12th week, we will have delivered a MVP, but not a complete application.
Then I setup a meeting with the scientist (client), presented to his team, went over the features, UI and the main security & compliance safeguards that will be baked in. During the presentation I realized that the client is NOT familiar with Agile Iterative development, I explained how they will be at an advantage, with a iterative delivery, than waiting for the whole 12 weeks to see anything. After a quick walk through of the roadmap, they realized that if they can iterate this product, they will be able to get more and more features and the capability can be upgraded at each iteration.
R - They happily agreed to the MVP in 12 weeks, and then we worked with them for the next 12 week delivery features. One of the best client we had, and had referred this product to be developed at other institutes too, and recommeded to CIOs at ohter institures
Share your approach to this question and unlock all community answers with detailed insights
Anonymous
Situation: During the device certification test process with our carrier customer, we encountered a large number of defects and could not meet the lab exit schedule
Task: I worked with the certification team to group the defects into different severity level and different defect categories to better proritize and identify a resolution plan to each
Action: We grouped the defects into four severity levels with level 1 as absolutely critical to close for lab exit, level 2 being acceptable for conditional lab exit with a resolution plan, and level 3 are defects that can been resolved in the MR release, and level 4 are information only or defects that could be waived by the customers. We worked with developers and engineering teams to provide Root cause analysis to identify the root cause and determine solutions. We also identified there are features that were outside of the MVP scope and we negotiated with the customer to deliver the features in a MR release in 6 months. This proposal actually worked better with the customer's launch strategy in which some new features were planned to be activated at a later time.
Result: We were able to resolve the severity level 1 defects on time and launched the devices per original schedule. The customer agreed to delay one new feature to a 2nd MR plan six months later. We delivered the fixes to the severity 2 defects in the 1st MR plan 3 months after the device launch. The customer was pleased that this mitigation plan allowed them to keep the original go to market schedule while maintaining the product quality.
Share your approach to this question and unlock all community answers with detailed insights
Anonymous
In the Meraki integration project, the supply chain process required significant optimization of the entire flow. To achieve this, most of the shipping-related process needed to be modified. However, the team lacked sufficient time to complete the work because the planned use of an adapter did not work, requiring me to redesign the flow.
With limited time remaining before system integration testing (SIT), the cross-functional teams and other tracks were ready to test their code, and management was unwilling to postpone SIT and Cycle 1 testing. Since there was an additional round of SIT and Cycle 2 testing planned, I decided to proceed with the changes that the team had already completed. We migrated the completed code to the test instance and communicated that only Phase 1 of the changes would be released initially, while the remaining changes would be delivered during Cycle 2 testing.
I ensured the Phase 1 delivery was designed to avoid impacting the end-to-end flow, allowing the other teams to proceed with testing their portions of the code. This approach ensured that other teams' deadlines were not affected. I also informed the cross-functional teams that the OTM and GTM changes were completed, and the remaining shipping-related code optimization would be delivered before Cycle 2 testing, along with the next round of SIT.
By taking this approach, I ensured that complete testing was not impacted and that the project stayed on track.
Share your approach to this question and unlock all community answers with detailed insights
Prepare for success with realistic, role-specific interview simulations.
Prepare for success with realistic, role-specific interview simulations.
Prepare for success with realistic, role-specific interview simulations.
Prepare for success with realistic, role-specific interview simulations.
Interview question asked to Software Engineers, Site Reliability Engineers, Full Stack Software Engineers and other roles interviewing at Wolt, Applied Materials, FleetSmith and others: How did you handle a situation where you couldn't meet a deadline?.