Program SenseProgram Management

What is the best way to assess the impact of a change in timelines?

Did you come across this question in an interview?

Answers

Expert Answer

Anonymous

6 months ago
4.6Exceptional
Ive had some great examples of this challenge.  I was working on a high profile project and there was pressure to deliver impossible requirements sooner than anticipated.  Immediately, i started a drill to identify the following:
1) understand what is required by order of importance for each task required to complete the project
2) understand how much time is required by each task
3) group with team members to explain impact of change in timeline
4) delegate to other team members with capacity to meet updated timeline
5) understand what can be de-prioritized to a later date
6) come up with a risk table to identify the owner of each task that is a blocker and assign an owner for that task as well as a due date and team responsible for that task.  Outline the high level steps needed to carry out the task
I worked on a major project where there was pressure to deliver earlier than that was possible.  The project had 60k stakeholders across the board.  Steps were taken to meet with the business owners of each area and understand the Minimum viable requirements needed for product delivery.  Some compromises were made.  An understanding was developed of what is not possible to achieve in the reduced timeline.  After reaching a compromise, the teams were apprised of the final agreement and subsequently weekly conversations and executive presentations were held discussing the project progress as well as an updated risk matrix to assess any risks and next steps.
Example of compromises that were made:  The business owners were demanding that all their data be migrated to the new platform, but technology is adamant that they can only move 20% of their data.  A compromise was made in that technology would deliver 20% of the data, but after the MVP is delivered, they will migrate the rest of the data in phases upto a year after initial MVP delivery.  Technology also offered to store the remaining data in a warehouse for the business to have access later on in the interim.  A detailed plan for how data can be accessed to the maximum satisfaction of the business to conduct their business in the meantime was provided and that led to a consensus and agreement with 30% increase in stakeholder satisfaction.
Example of Risk Table columns to manage risks:  I created a risk matrix which would identify the item at risk along with the names of owners responsible for completing the tasks.  The purpose of the table is to keep track of blockers along with a timeline and steps needed to remove the blocker.  The risk table was filled out weekly and communicated to stakeholders for transparency.
Example of UAT table:
Itemized list of all items needed for each area of focus as well as sign off owner.  UAT sign off owners need to be identified who can sign off on the requirement as being good for product launch.
I created a table which Calculated the percentage of progress of UAT sign off to see progress.  For example if there are 20 items to achieve and 10 have received sign off then the sign off percentage would be 50%.
I helped Prepare an executive presentation to leadership to highlight the high level project progress as well as listing out the risk items and noting down any steps that are being taken to reduce any blockers to success.
The final result was that I got CEO recognition for the work done and the project is now viewed as a template for how the rest of the projects should be handled across the organization.

Anonymous

3 months ago
4.2Exceptional
In my previous job, I was in charge of a new TCU release but, just one month before PVT date our customer decided to change some product specifications, but they still wanted us to get the project finished within the original schedule. The changes impacted on Bluethooth, Wifi, and GPS modules,
T: So I immediately met with the core-team. Some team members suggested to go back to the customer to request an extension. So, I analyzed the situation and I suggested to keep working to meet the new demand by using our expertise and lessons learned from other projects to fix the issue.
A: To address the situation, I worked overtime every day for a month and led a special task force. I established daily opening and closing meetings with the team to define priorities and prevent duplicated efforts among the cross-functional team. I decided with the team to split the problem into two branches: hardware (HW) and software (SW). From the HW perspective, we agreed to reuse existing compatible validated and qualified modules to save time. SW was more complex, so we chose to release the product with only the main functionalities initially, focusing on the lower layers of SW. During the one-month lead time for shipment by boat, we utilized that time to complete the remaining applications and functionalities, which were then updated via OTA.
R: Finally, We achieved the goal and completed the project successfully and our team was awarded with the best Performer Team award.

Anonymous

3 months ago
4Strong
I would assess the impact the change has on the projects RAID register (Risks, Assumptions, Issues, Dependencies). If the change to the timeline impacts the critical path (determined by mapping the critical path on a Gantt chart) then there is an impact to the delivery date of the project. I would work with the stakeholders to understand the root cause of the change (technology, resources, budget, quality) and develop mitigations. For example, it is possible/better to reduce scope or increase resources to meet the planned timeline? As an example, I was working on a project where we found that significant quality issues with a voice to text service in some languages we were evaluating. We had to integrate a new solution to meet the quality bar. I worked with the stakeholders to phase the delivery so the languages that were working accurately were shipped on time while the team worked on integrating the new solution with the remaining languages which we then shipped 2 weeks later.

Anonymous

3 months ago
4Strong
The best way to assess the impact of  change in timelines, would be to check how the shift in timeline has affected the critical path of the project, and determine how it changes the overall delivery schedule. For example while I was working at Intel the delivery of 2 important ICs was delayed  by 2 weeks, this impacted few internal teams in their assembly and board testing schedule. However I made sure that our team was transparent with the stakeholders and kept them posted on all activities. I managed to arrange for extra test equipment so that parallel testing could be done once the IC arrives.
Meanwhile I also informed the stake holders that we were looking into expedited shipping options and checking with other vendors for the earliest availability of those ICs

Anonymous

3 months ago
3.6Strong
Identify their impact on critical paths. Understand which critical paths are affected and if there is any way to reduce the impact. Communicate the situation to the team and stakeholders. Request additional resources and help if possible. 

Anonymous

4 months ago
3.6Strong
The impact of change in timelines is best assessed in terms of the impact it will have on the KPIs/metrics of the task attached with the time change. The metrics can be revenue, a conversion metric, launch etc.

Anonymous

5 months ago
3.6Strong
When there is a new scope request to be included in middle of sprint / project work timelines . Its important to Identify the  technical aspect of new scope , discussion with the team of breakdown of the work & current impact to workflow . Prioritization & timelines needs to be addressed with Product Owners / Business & Tech Team  .   Have a discussion with the team to determine  breakdown of the work in subtask & also the additional capacity required for completing the task / work & timelines adjustment required for competing the additional scope change . Present a updated plan that will give a clear picture - on Scope of work to the completed ( breakdown of the task & timelines ) , Team dependency  & alignment ( internal & external  ) and highlighting the risk mitigation strategy . Publish the plan to all the stakeholders with outlining the timelines , objectives & release plan , Alignment with all the internal & external team 

Anonymous

8 months ago
3.4Strong
Identify all the critical tasks that would be impacted by a change of timelines. Work on a risk mitigation plan and review the impact with the team.

Anonymous

8 months ago
3.4Strong
Determine the impact on critical path and existing float within your schedule, determine work load and plan for your personnel resources, review risk and mitigation plans
  • How do you assess the impact of a change in timelines?
  • What is the best way to assess the impact of a change in timelines?
  • How would you estimate the impact of changing timelines?
  • If there is a change in timelines, how would you assess the impact?
  • What is your strategy for assessing the impact of a change in timelines?
  • In what ways can you determine how a change in timelines will impact your project?
  • When a timeline is changed, how can you determine the impact?
  • How do you evaluate the impact of a change in timelines?
  • How do you measure the effects of shifting project deadlines?
  • Can you explain how you assess the effect of a change in timelines on the overall outcome of a project?
  • What methods do you use to determine the impact of timeline changes on project performance?
  • Have you ever experienced a situation where a shift in timelines had a significant impact on project success? How did you evaluate this impact?
  • Could you give an example of how a timeline change can affect project quality, budget, or timeline delivery?
  • How do you gauge the impact of timeline changes on your project's progress?
  • What are the factors you consider when assessing the impact of timeline changes?
  • Do you use any specific metrics or tools to analyze the effects of timeline changes on project performance?
  • How do you make an assessment of the implications of timeline adjustments?
  • In your opinion, what's the most efficient way to evaluate the impact of timeline changes and ensure project success?
Try Our AI Interviewer

Prepare for success with realistic, role-specific interview simulations.

Try AI Interview Now

Interview question asked to candidates interviewing at top companies: What is the best way to assess the impact of a change in timelines?.